A change order is a short written amendment to the contract: what changes, what it costs, how it moves the schedule — signed by both sides before the extra work starts. Here is how to write one that gets signed and paid, with a fully priced example.

In short
  1. Number it and tie it to the contract
  2. Say who asked for the change and why
  3. Describe the work so a stranger could price it
  4. Price it line by line
  5. Show the contract sum before and after
  6. State the schedule impact
  7. Say when it gets paid
  8. Sign it before the work starts
Free change order template (PDF, Word, Excel)

Before you write: read your contract’s change clause

Most contracts already say how changes work — who may order them, how they are priced, the markup allowed and how fast you must give written notice of a change or a claim. A change order that ignores those rules is easy to reject. Thirty seconds with the clause tells you the markup to use and the deadline you are working to.

The 8 steps

  1. Number it and tie it to the contract. Give every change order a sequential number (CO-001, CO-002…) and name the project, the job address and the date of the original contract. The number is how both sides refer to it later, on invoices and in disputes.
  2. Say who asked for the change and why. Owner request, architect’s instruction, hidden site condition, code inspector, design error. The reason decides who pays: an owner’s upgrade is billable, a mistake in your own work usually is not.
  3. Describe the work so a stranger could price it. Location, quantity, material, what is added and what is removed. “Extra electrical” cannot be priced or checked; “add one 20A GFCI outlet on the east face of the kitchen island, new home run from the panel” can.
  4. Price it line by line. Labor hours × rate for each trade, materials, equipment, subcontractor quotes — then overhead and profit as a stated percentage. Use the markup your contract allows; if it says nothing, state yours on the form.
  5. Show the contract sum before and after. Original contract sum, total of previous change orders, this change order, new contract sum. A running total stops the “how much is this job now?” argument at the final invoice.
  6. State the schedule impact. Number of working days added (or “no change”) and the new completion date. Leaving it blank invites a later claim for delay, against you.
  7. Say when it gets paid. With the next progress invoice, on completion of the change, or a deposit before ordering materials.
  8. Sign it before the work starts. Contractor and owner (or GC, if you are a subcontractor) sign and date it. Work done on a verbal go-ahead is the most common reason extras go unpaid.

Worked example

A kitchen remodel. At the walkthrough the owners move a counter appliance and ask for an outlet on the island. The contractor writes it up before leaving the site.

ItemQty / hoursRateAmount
Electrician labor3 h$95.00$285.00
Wire, box, GFCI device, plate1 lot$68.40$68.40
Drywall patch (carpenter)1 h$65.00$65.00
Subtotal$418.40
Overhead & profit15%$62.76
This change order$481.16
Change order no.
CO-003 — Hillcrest Kitchen Remodel, contract of Sep 2, 2026
Requested by
Owner, on site walkthrough
Description
Add one 20A GFCI outlet on the east face of the kitchen island: new home run from panel, box, device and cover plate. Includes patching drywall at island base.
Reason
Owner request — counter appliance location moved.
Contract sum
$38,400.00 original + $1,215.00 previous change orders + $481.16 this change order = $40,096.16
Schedule
+1 working day; new completion date Nov 7, 2026
Payment
With the next progress invoice. Work starts after both parties sign.

See it on the form: filled-in change order example (PDF).

Descriptions that get signed — and ones that start arguments

VagueSpecific
Extra electricalAdd one 20A GFCI outlet, east face of island; new home run from panel
Upgrade tileReplace specified 12×24 porcelain with owner-selected 3×12 ceramic subway, 86 sq ft, master bath walls; extra labor for smaller format
Fix rotRemove and replace 14 linear ft of rotted rim joist found behind siding on north wall (hidden condition, photos attached)
Remove deck stainCredit: owner will stain deck; delete stain and labor from scope (– $1,250.00)

Three ways to price a change

If the owner won’t sign before the work has to happen

Sometimes the work cannot wait — the wall is open, the inspector is coming. Get the instruction to proceed in writing (a signed note or a reply email is better than nothing), track the cost on signed daily T&M tickets, and write the change order as soon as the cost is known. Standard contract forms such as the AIA general conditions provide a document for this situation, the construction change directive: the owner orders the work now and the price is settled later.

California home improvement contracts: the rule is in the statute

For home improvement contracts in California, the change order requirements are written into the Business and Professions Code:

“A change-order form for changes or extra work shall be incorporated into the contract and shall become part of the contract only if it is in writing and signed by the parties prior to the commencement of any work covered by a change order.”

“(1) The scope of work encompassed by the order. (2) The amount to be added or subtracted from the contract. (3) The effect the order will make in the progress payments or the completion date.”

Section 7159.6(c) adds that missing these requirements does not by itself stop a contractor from recovering payment for work done under remedies against unjust enrichment — but it turns a signed price into a lawsuit. Other states have their own home improvement rules; check yours.

Statute text checked on October 22, 2026. This page is general information, not legal advice.

Mistakes that cost contractors money

Write and sign it on your phone, on site

Change Order Form: T&M Ticket is an iPhone app for change orders and T&M tickets.

Questions

What should a change order include?

A change order number, the project and contract it amends, who requested the change and why, a specific description of the work, the cost broken into labor, materials, equipment, subcontractors and markup, the contract sum before and after, the effect on the schedule, payment terms, and both parties’ signatures and dates.

Who writes the change order?

Usually the contractor who will do the work prices it and writes it; the owner (or the GC, for a subcontractor) reviews and signs. On larger projects the architect or construction manager may issue it on a standard form.

Can I start the extra work before the change order is signed?

You can, but you carry the risk of not being paid for it. In California, a home improvement change order becomes part of the contract only if it is in writing and signed before the work it covers begins (Business and Professions Code § 7159). If the price cannot be agreed in time, record the work on signed daily time and materials tickets and roll them into a change order.

How do I write a change order that reduces the price?

The same way, with the amount as a credit: describe the work removed, show the deduction (for example “– $1,250.00”) and the lower new contract sum. Owners sign credits quickly; it keeps the paperwork consistent.

What markup is normal on a change order?

It is whatever your contract says. Many contracts fix a percentage for overhead and profit, often with a smaller one on subcontractor work. If the contract is silent, state your percentage on the change order so it is agreed when signed.